Welds, faulty components, corrosion: French nuclear power in ever greater difficulty

Welds, faulty components, corrosion: French nuclear power in ever greater difficulty

Energy · ·

Inspections by the Nuclear Safety Authority continue to find defects at French plants. The Flamanville site has been shut down.

French nuclear power is increasingly at the centre of a storm. Following the halt to construction work on the new Epr reactor at Flamanville, on the English Channel, ordered last July by the French Nuclear Safety Authority (Asn) over problems related to certain welds, on 11 September the entire plant was placed under "enhanced surveillance".

nucleare francia
France has abandoned research into fourth-generation reactors © Alexandra Beier/Getty Images

The Flamanville nuclear plant under "enhanced surveillance"

The decision was justified by the French regulatory body with "the difficulties encountered by Edf (the company that manages the nuclear site) since mid-2018". And the problems identified concern not only the new reactor under construction, but also the two 1,300 MW units that have been in operation since 1979. The plant has in fact long been subject to its third ten-yearly inspection, which represents a comprehensive check-up of the entire facility.

L'Autorité de sûreté nucléaire (ASN) a annoncé mercredi avoir placé la centrale nucléaire de Flamanville (Manche) sous "surveillance renforcée", estimant qu'EDF y rencontre des difficultés sciencesetavenir.fr/nature-environ…

The objective is to determine whether the plant can operate for a further decade. Previously, Asn's director general, Olivier Gupta, had called for "an action plan" to strengthen internal controls. He highlighted "the deficiencies identified from a technical standpoint" and "the high number of significant events related to maintenance and oversight failures on the part of third-party companies, poor management of certain operations and insufficient quality of the documents submitted". This "plan" was delivered by Edf on 25 August. In the document, the company admitted to "sharing" the regulator's criticisms.

Problems with the steam generators

But the problems facing the French nuclear sector are multiplying. On 10 September, Framatome came under scrutiny (formerly Areva Nuclear Power, owned by Edf since 2018). And once again the problems are related to welds — not on the Epr reactor at Flamanville this time, but on the steam generators. These are a fundamental component of reactors and of considerable size: 22 metres tall and weighing on average 465 tonnes. Their role within the plants is crucial, as they are the components that convert water into steam, which in turn drives the turbines to generate electricity.

Even more worrying is the fact that the defects identified by the Nuclear Safety Authority concern not only new material not yet installed, but components already in service. The regulatory body spoke of "around twenty steam generators potentially affected, manufactured from 2008 onwards". To date, nine have been found to contain non-conforming materials.

A German supplier of nuclear components involved

The problem is directly linked to the size of the steam generators: so significant that, during the construction of the plants, the welds had to be carried out on site. "Once completed," explains the daily Le Parisien, "covers fitted with electric heating elements are applied to them, which are needed to bring the temperature to 595–620 degrees in order to homogenise the welds themselves." It is at this stage that Asn identified the problems, which also involve a German supplier of Framatome, Weld Therm.

Edf may now decide to use components manufactured by another company. According to the French press, this would represent "an industrial catastrophe" for the former Areva Nuclear Power, which has already been forced to contend with a significant drop in orders for two years.

Centrale #nucléaire #EDF de #Flamanville : l'ASN place sous "surveillance renforcée" le site en exploitation (réacteurs 1 et 2) -> asn.fr/Informer/Actua… @EDFFlamanville @EDFofficiel [image : DR]

The Flamanville plant is currently shut down

The latest development once again concerns the Flamanville plant. On Wednesday 18 September, Asn inspectors found traces of corrosion on certain emergency systems. As a result, reactor 1 was shut down. This came while reactor 2 had already been switched off as part of the inspection procedures for the ten-yearly review (restart is scheduled for 5 December). This means that, as of today, the site is no longer generating any power.