The next largest offshore wind farm in the world will be, once again, in the UK

The next largest offshore wind farm in the world will be, once again, in the UK

Environment · Redazione ·

At 3.6 gigawatt-hours, the Dogger Bank offshore wind farm will be capable of powering the equivalent of 6 million homes.

Work to install the first wind turbines for the world's largest offshore wind farm off the north-east coast of England has begun. Energy company SSE announced the news after installing, in early August, the first of what will become an immense forest of turbines in the middle of the sea — around 120 kilometres from the coast — an image of the push for renewables being championed by the UK.

The campaign to install the first of our 277 wind turbines is underway. This is a major advance in the offshore wind industry and a boost to the transition to a cleaner, more secure energy system in the UK.

@sserenewables @Equinor_UK @eni

A new record-breaking offshore wind farm for the UK

Once complete, the Dogger Bank wind farm — worth £9 billion, over €10 billion — will be more than double the size of the second-largest offshore wind farm currently in operation. The 3.6 gigawatt installation will be capable of powering the equivalent of 6 million British homes thanks to its 227 turbines. In doing so, the UK will equal and surpass the record set no later than last year, when the Hornsea 2 wind farm came into operation approximately 69 kilometres off the Yorkshire coast, itself surpassing its elder sibling, Hornsea 1.

"It's a fantastic day for us," Alistair Phillips-Davies, chief executive of SSE, told the BBC on Thursday. Phillips-Davies said that future wind farms will require government subsidies to keep pace with rising material and service costs driven by significant inflation in the UK economy: "The government needs to put in place the flexibility to ensure that we can still build these wind farms," he said. "We need to remember that the price of energy produced by wind farms is still much lower than what we see coming from imported fuels, and in particular from gas."

New transition subsidies following the halt of the Norfolk wind farm

The start of work on Dogger Bank follows a rather difficult July for the country's transition progress. The global economic situation, which has led to rising costs across the supply chain for certain materials and higher interest rates, had in fact caused a sharp slowdown in plans for a giant offshore wind farm off the Norfolk coast. Swedish energy company Vattenfall, which was overseeing the work, announced the suspension of operations on an infrastructure that at full capacity would have powered the equivalent of 1.5 million British homes.

Vattenfall says it is stopping British Norfolk Boreas offshore wind farm reut.rs/44SuJE8

In response, the UK government decided on a £22 million increase to the grant fund supporting new renewable energy projects, bringing the total budget to £227 million. A decision that, according to Energy Secretary Grant Shapps, "will help grow our economy, making the UK the first choice for investors in renewable energy projects and securing skilled jobs for future generations."