The Messina Strait bridge faces a “sea” of formal complaints

The Messina Strait bridge faces a “sea” of formal complaints

Rights · ·

Opposition to the Messina Strait bridge is growing. Committees and professionals file two new formal complaints.

The Messina Strait bridge continues to inflame passions. Following the formal complaint filed in February by Alliance of Greens and Left MP Angelo Bonelli, PD secretary Elly Schlein and Italian Left secretary Nicola Fratoianni — after which the Rome prosecutor's office had opened an inquiry with no alleged offence and no suspects — two further formal complaints have been lodged, one with the Reggio Calabria prosecutor's office and another with the Messina prosecutor's office. Both have also been sent to the Court of Auditors. In Reggio Calabria the complaint was filed by the committees representing people whose homes will be expropriated and by the local branch of the Democratic Party, while in Messina it was filed by forty lawyers, university professors and professionals.

Furthermore, 13 April marked the deadline for observations on the Messina Strait bridge. In addition to a substantial 534-page document submitted by environmental associations, several critical issues were also raised by the Democratic Party (PD) of Villa San Giovanni (the municipality from which the bridge would depart on the Calabrian side) and the metropolitan city of Reggio Calabria. These issues concern the project in terms of its impact on biodiversity, the atmosphere, water, soil and subsoil, pollution including noise pollution, public health, the protection of cultural and natural heritage, and monitoring, as reported in the daily ReggioToday.

ponte-sullo-stretto-render
This is what the Messina Strait bridge will look like, according to the designers © Società Stretto di Messina

The Messina Strait bridge construction sites will have "strongly negative" consequences

Regarding the observations, the most anticipated were those from the Municipality of Villa San Giovanni. These include the positions of local associations — among them environmental groups and citizens' movements — as well as the opinions of technical experts and professionals in the sector. According to the municipality, the construction works "will have strongly negative consequences on the quality of life of residents, of adjacent businesses, and could lead to an overall decline in the quality of life of the community affected." In short, the bridge "will alter the urban character of the unified city" and the construction areas "will consume land that has until now been preserved from human development." Among the municipality's requests is one concerning certainty over the project's timeline, so that it does not remain "an eternally unfinished work."

Beyond the general recommendations, the documents submitted to Mase (the Ministry of the Environment and Energy Security) identified several shortcomings with respect to the 2013 compliance review, ranging from the environmental and landscape significance of the strait to the recent discovery on the seabed at Cannitello of a forest of the extremely rare giant alga laminaria ochroleuca, a protected species. In short, a loss to the natural capital of the Strait and to the ecosystem services it provides.

The documents also note design deficiencies relating to the management of rainwater, the management of excavated earth and rock, the runoff of construction-site water laden with pollutants into the sea, the consequences for coastal structures, and the replenishment of the Calabrian shoreline. A specific concern is raised regarding the fault line between Punta Pezzo and Cannitello, which caused the catastrophic earthquake of 1783 and has not been accounted for in the project.

And then two more formal complaints to the prosecutor's office

And then there is the matter of expropriations. First and foremost, some have pointed out that the current procedure for removing residents from areas affected by the construction is based on an EIA (Environmental Impact Assessment) process that concluded in 2013 with a "failure to reach a positive conclusion": this is what the legal association GriG states in a submission sent to Mase, in which it highlights the conclusion reached by technical experts more than 11 years ago — namely, the "impossibility of expressing an assessment of environmental compatibility" with regard to the natural habitats of the area in question. The association therefore calls for that EIA procedure to be declared lapsed, "due to the unproductive passage of time."

Finally, compared with the complaint filed by Bonelli, Schlein and Fratoianni — which called for greater transparency on the costs of a project described as "anachronistic" — the two new complaints contain more detailed information based on the report of the scientific technical committee that examined the most recent version of the project over the past few months. The committee issued a favourable opinion; however, in its concluding report it included a series of recommendations addressed to the Eurolink consortium, which holds the contract, ahead of the submission of the executive project expected in the coming months. In total, the scientific technical committee had made 68 observations on the bridge project. "The 68 recommendations, which fill the entire content of the scientific committee's document, demonstrate the full awareness among the committee's own members of the unfeasibility of the project, given the current state of scientific knowledge and the experiments carried out," are the words of the person who filed the complaint, as reported by Repubblica.

In addition, the complaint calls on the prosecutor's office to examine all contracts and clauses agreed between the Stretto di Messina company and the Eurolink consortium, with particular attention to the "additional agreements" that determine liability for extraordinary costs in the event of unforeseen circumstances. These agreements have never been made public, and the group of professionals who filed the complaint suspects that the final cost will considerably exceed the projected 14.5 billion euros.