The renovation of the bobsled track for the Milan Cortina 2026 Olympics has become a major issue: at stake are environmental impact and millions in public funding.
The tender to begin renovation work on the facility drew no bids
Costs keep rising and work must begin by September to meet deadlines
There are serious doubts about the usefulness of the facility, which will have a severe environmental impact
Just over two and a half years remain until the opening of the Milan-Cortina Winter Olympics, scheduled for 6 February 2026. Visiting the official Olympics website, among the venues that will serve as "theatres of the games", under the Cortina section, one finds the Cortina sliding center — the facility that is meant to host the bobsled, luge and skeleton events, named after Eugenio Monti, a legend of Italian bobsled who won six Olympic medals and ten world championships between 1957 and 1968. A structure that, as the site explains, will be completely renovated and will have a capacity of over five thousand spectators. All very impressive on paper. All dramatically only on paper, for now. This is because work on the track has not even begun and no one seems willing to take it on. The timeline is tight because everything must be ready by December 2024 and, finally, there is the elephant in the room: the environmental impact of the new track, which would not only run counter to the stated aim of these Olympics to be "the most sustainable ever", but risks leaving an enormous burden on Cortina and its mountains.
The Milan-Cortina 2026 logo during the closing ceremony of the last Winter Olympics in Beijing 2022 (Photo by James Chance/Getty Images)
From the original bobsled track plan to the current situation
The idea was to launch a major renovation plan for Cortina's historic bobsled track, according to the Coni, the Italian National Olympic Committee. Built in 1923, renovated several times and definitively abandoned in 2008 — when the bobsled track most used in Italy was the one in Cesana, in Piedmont, built specifically for the Turin 2006 Olympics at a cost of 110 million euros and, likewise, abandoned since 2011.
Since falling into disuse, Cortina's bobsled track has been reclaimed by nature: moss has grown over the concrete, rain and frost have damaged it throughout, it is broken in many places, and for local residents it has become the perfect spot for a walk (as described in this reportage by Il Post). But because of its history, the fact that it is named after one of Italy's most decorated athletes, and because "it's in Cortina", the organising committee decided to focus on this track for the 2026 Olympics.
The renovation work required is enormous. Almost nothing of the existing track can be saved. Safety requirements, compared to a hundred years ago, are far more stringent, and the track layout and curves will need to be redesigned and widened. Much of the track will have to be modified and therefore widened for safety reasons, the space dedicated to the facility will grow ever larger, amounting to the near-total clearing of the wooded area surrounding it. This, combined with the high costs, has caused the Veneto region's original project to collapse entirely — a project that had envisaged the creation of a large park around the track with the aim of keeping it usable after the Olympics. The initial cost was 85 million euros, but in October 2021 the plans changed and it was decided to rebuild only the bobsled track at an initial cost of 61 million.
The deadlock of recent years, the uncertainty over what to do, and the resulting delays have driven the cost up: it has reached 93 million, even though a few months ago Veneto president Luca Zaia had said it could rise to as much as 120 million euros.
And so we come to the latest news on the Cortina track: on 31 July last, the tender for the award of the renovation work expired, but no company submitted a bid, as announced by Simico — the Società infrastrutture Milano Cortina 2026, which has been entrusted with the management of the Olympic infrastructure. This is a major problem because, according to estimates, making the Cortina track operational requires 807 days of work. The International Olympic Committee (IOC), in fact, wants all facilities ready by 2024 so that reliability tests can begin. This means that work will have to start no later than the end of next September. But at present, it is not even known who will carry out that work.
Simico has now launched a negotiated procedure through which it will seek companies on the market capable of building the new track, whose demolition had in any case begun last March. The companies identified will be asked to submit a bid, at which point the best one will be selected. Provided that someone actually submits one.
What is the environmental problem
From the outset, well before the current situation was reached, several local organisations had raised doubts about the merits of the project, questioning whether it actually made sense to embark on such a complex renovation, above all on grounds of environmental impact.
According to data from the Club alpino italiano (Cai), deforestation would affect over 25,000 square metres of vegetation and it would be necessary to draw more than three thousand cubic metres of water from municipal reserves to form the ice, in a context already under stress from a water standpoint and where snowfall decreases every year. To all of this must be added the polluting emissions and the use of chemical substances required for the construction work and for the track's refrigeration systems.
Cortina's residents appear to be aware of these issues, as shown by a survey from August 2021 conducted by the Comitato civico Cortina: 60 per cent of inhabitants are convinced that the environmental impact is too high. Not only in order to protect the mountain and the forests, but also because this kind of project would be entirely self-serving, as demonstrated by the previous abandonment of the Cortina track itself, as well as the more recent one in Piedmont. Moreover, the number of people in Italy who practise these disciplines is shrinking all the time: fewer than 50. Too few to envision a life for the facility beyond the Games.
Alternatives to the Cortina track
The main solution, proposed for some time by various organisations, is to move the bobsled, luge and skeleton events to Cesana, in Piedmont, by refurbishing the facility built for Turin 2006. Both the president of Piedmont, Alberto Cirio, and the mayor of Turin, Stefano Lo Russo, had in some way signalled openness to hosting these disciplines, but the response from Coni first and from Veneto subsequently was a firm rejection of this option. Without bobsled, Cortina would be left with only alpine skiing and curling and, in the view of President Zaia, the city's role in the Olympic landscape would therefore become too marginal.
The other option is to abandon any work on the Cortina track altogether and begin negotiations to use the facilityat Igls, near Innsbruck, in Austria. It is the alternative closest to Cortina (around 150 kilometres away) and would save a great deal of money while avoiding damage to the territory, but at the same time would represent a serious "admission of failure" on the part of Coni and Italy, reduced to seeking hospitality abroad due to their inability to manage the situation. The IOC, for its part, is not concerned about the facilities being located in Italy specifically or necessarily being new, so much as having them up to standard and usable for the Olympics without any hitches.
There is also a third option, more drastic but with a precedent: scrapping the bob, luge and skeleton events from the Olympic programme altogether. This is what happened at the 1960 Winter Olympics in Squaw Valley, California, when the American organisers decided they had no intention of building a bobsled track, both because of the high cost and because of the impossibility of repurposing the facility once the Games were over. The IOC consequently removed those disciplines from that edition, awarding no medals.
For now, the facts remain: the Cortina bobsled track represents a major problem for the 2026 Winter Olympics. Andtime, meanwhile, is running out.